GJPS Board of Education and District Leadership break ground for the new Lincoln High School.

Phase Two Building Projects

DISTRICT: Master Facilities Plan

Side Menu


GJPS Email Newsletter Sign-up

Sign-up to get construction updates and interesting news from around the district delivered to your inbox through our weekly updates.

If you are a parent or caregiver of a child in the Gahanna-Jefferson Public Schools, you should already be receiving our email updates and newsletters and do not need to sign-up again.

If you are a community member who does NOT have a child in the Gahanna-Jefferson Public Schools, then please complete the form and you will be added to our email newsletter list.





 

PHASE TWO: BUILDING PRIDE FOR OUR FUTURE

.

PHASE TWO OVERVIEW

 

In November of 2020, voters in the Gahanna-Jefferson Public Schools district approved a 10.69 mills bond and operating levy to fund Phase Two of the GJPS Master Facilities Plan.

 

PHASE TWO OF THE MASTER FACILITIES PLAN INCLUDES:

Additions and Renovations to High Point and Blacklick Elementary
Space for an additional 225 students in each building.

Additions and Renovations to Middle School East
Space for an additional 175 students.

New Lincoln High School on Current Site
Space for an additional 600+ students. 

Operating Funds
Filling the gap created by state cuts, increased technology costs and additional staffing due to enrollment growth.


 

 


   PHASE TWO INFORMATION BROCHURE  .

 

Phase Two Community Update December 2022 (PDF)


 NEW GLHS FLY THROUGH   .

Take a look inside the NEW GLHS with this latest FLY THROUGH video! While many of the specific material, furniture and color choices are not finalized, you will see many of the incredible features that our new building will offer.

 


      PHASE TWO FINANCIAL & COMPLETION UPDATE   .

To hear complete conversations on the current work and cost of all of our Phase Two projects, we encourage you to attend our Finance and Facilities Board of Education Committee Meetings on the third Tuesday of each month at Clark Hall.

You can also view the livestream for each Finance and Facilities Committee Meetings from your computer or mobile device.

MOST RECENT FINANCE AND FACILITIES COMMITTEE MEETING
November 15, 2022

 


MONTHLY PHASE TWO CONSTRUCTION SNAPSHOT

October 2022 Construction Financial Report

November 2022 Construction Financial Report

December 2022 Construction Financial Report

December 2022

BLACKLICK ELEMENTARY
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  12/15/2022  12/30/2022  12/30/2022
 CONSTRUCTION COST  $9,230,000  $10,599,258  $10,622,959

 

HIGH POINT ELEMENTARY
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  12/15/2022 01/12/2023  01/13/2023
 CONSTRUCTION COST  $9,410,000  $11,466,098  $11,481986

 

MIDDLE SCHOOL EAST
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  01/15/2024 01/15/2024 01/15/2024
 CONSTRUCTION COST  $8,840,000  $10,331,360  $10,331,360

 

GAHANNA LINCOLN HIGH SCHOOL
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  06/16/2025 06/16/2025  06/16/2025
 CONSTRUCTION COST  $158,190,000  $170,221,722  $170,221,722

 

GLHS STADIUM
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  08/02/2023 09/04/2023  09/04/2023

 

BLACKLICK ATHLETIC COMPLEX
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  06/02/2023 06/30/2023 06/30/2023
 CONSTRUCTION COST  $5,000,000  $8,266,072  $8,266,072

 

GLHS DEMO AND PARKING
  ORIGINAL   LAST REPORT  CURRENT
 COMPLETION DATE  07/31/2026 07/31/2026  07/31/2026

 


    PHASE TWO CONSTRUCTION AND RENOVATION NEWS  

 

Summer Improvement Projects

Summer Improvement Projects

Date: 5/12/2023

GJPS Gearing Up for a Busy Summer

Phase Two February Photo Highlights

Phase Two February Photo Highlights

Date: 3/1/2023

Enjoy this roundup of construction pictures taken during the month of February from Phase Two projects around the district.

February Construction Updates

February Construction Updates

Date: 2/24/2023

February 2023 Stadium construction Update

Moving Day for the One-Room Schoolhouse

Moving Day for the One-Room Schoolhouse

Date: 2/16/2023

The One-Room Schoolhouse has recently been moved to a new location on Havens Corners Road.

Phase Two Update Mailed to Residents

Phase Two Update Mailed to Residents

Date: 1/15/2023

Over Winter Break, this Phase Two informational brochure was mailed to GJPS residents.

Phase Two December Photo Highlights

Phase Two December Photo Highlights

Date: 1/5/2023

Enjoy this roundup of construction pictures taken during the month of December from our Phase Two projects around the district.

New GLHS Sneak Peek

New GLHS Sneak Peek

Date: 12/12/2022

Take a look inside the NEW GLHS with this latest FLY THROUGH video! While many of the specific material, furniture and color choices are not finalized, you will see many of the incredible features that our new building will offer.

Phase Two November Photo Highlights

Phase Two November Photo Highlights

Date: 11/30/2022

Enjoy this roundup of construction pictures taken during the month of November from Phase Two projects around the district.

November Construction Update

November Construction Update

Date: 11/11/2022

November 2022 Stadium Construction Update

Phase Two October Photo Highlights

Phase Two October Photo Highlights

Date: 11/2/2022

Enjoy this roundup of construction pictures taken during the month of October from Phase Two projects around the district.